The "Renewable is Doable" alternative to nuclearFrom the Greenpeace/Pembina document:
 |
| Table A7 Renewable is Doable .... |
Analysis conducted by the OPA in 2012 shows that it is cheaper to build new gas plants at current prices than to refurbish the Darlington or Bruce nuclear stations. The analysis in this report also shows that at 10 cents per kWh, a portfolio of conservation and green energy is also competitive with nuclear refurbishment.
Some aspects of the report's "green portfolio" are difficult to argue with - and those are probably the least realistic:
- Hydro is most everybody's preferred generator, but locations are probably not readily available, particularly those which would produce the 55% capacity factor (CF) the Pembina/Greenpeace table indicates. I calculate recently 36% has been about average for the non-regulated hydro in Ontario/
- Biomass, biogas and landfill might be doable, but it begs the question why would non-dispatchable wind and solar be pursued if these dispatchable options are realistically priced in the document (and low-carbon)
- The 450MW of "additional efficiency and conservation" is shown as producing full out 24X7 all year long to get to 3,942GWh - that's not a serious estimate of anything. Discounting this frivolous negawatt total, and assuming hydro location might be found to produce at the average 36% the total production drops to 9951GWh, and the average cents/kWh rise to 14.19.
- Darlingon's actual capacity factor is far higher than the 85% used to make renewable doable ... it's been 91% over the past 3 years (and 96% in the months of July; 98% in the months of January).
If we let the claim on "Combined heat and power" go, the prices become about the same, but to get those prices the new build option needs to produce about 16TWh a year while the renewable is doable option only needs ~10 TWh to get to that price.
But we can't let the implied claims on "Combined heat and Power" component go at an estimated 8.5 cents/kWh - or any other price.
Combined heat and power (CHP)
There are very few sources of information on costing combined heat and power projects. We do know there are CHP generators amongst the "non-utility generator", or NUG, contracts. These contracts were signed by Ontario Hydro probably because politicians (Peterson/Rae) had decided private supply would be cheaper than mega-projects like the delayed, at the time, Darlington. When Ontario Hydro was broken up, an "unfunded liability" was one result: of the $19.4 billion in liabilities considered to be unsupported by assets, $4.3 billion was due to the expected losses expected to be incurred during the remainder of the NUG contracts. [4]
Dwight Duncan, as Minister of Energy in the early years of the McGuinty regime (2003-) designed and implemented a hybrid system where
"Fixed prices for a large part of the energy consumed in the province would keep the overall blended price for electricity relatively stable.” [5] The fixed prices were on the public generator's large legacy hydroelectric stations, and it's nuclear units.
In 2013 generation from Darlington's nuclear units i
s reported to be receiving 5.7 cents/kWh, while the NUGs churn away at rates likely far more than double that.
Newer combined heat and power supply has not been so cheap as double the price of OPG's nuclear output. During the Darlington new Nuclear Power Plant Project Joint Review Panel hearings [6], Mr. Jennings, "the Assistant Deputy Minister of Regulatory Affairs and Strategic Policy Division at the Ontario Ministry of Energy" said this about CHP:
Newer combined heat and power projects are not so cheap as that it is often suggested that combined heat and power is very cost effective, very easy to do and there is a lot of potential for it. This competitive RFP was for 1,000 megawatts. They ended up only getting 414 megawatts of responses, so those were all taken.
In terms of the cost in that plan, they ranged. The cost of the products procured ranged from about 11.5 cents up to about 24 cents a kilowatt hour, so these are quite expensive projects.
There have been negotiations with some individual proponents since then. They would tend to be at the higher end of that range.
Certainly the claimed 8.5 cents/kWh in "Renewable is Doable" isn't realistic; neither is the implied 80% capacity factor. The "Green Portfolio" portfolio presented by Pembina and Greenpeace has, basically, 300 MW of dispatchable generation for 2200 MW of vRES capacity - so when it's windy or sunny, the CHP isn't likely to be operating efficiently.
To utilize CHP efficiently, clients are required for electricity, and for heat. This explains the variety of project pricing. It dosn't explain why CHP would be added in a summer peaking jurisdiction, which Ontario is - or how it would achieve a high utilization rate without an industrial client for the steam.
Renewable is doable does provide an estimated cost for new nuclear - one I'd expect is high, but not inconceivable.
It does not provide a properly costed and realistic alternative.
CarbonRenewable is Doable contains the word carbon 6 times; always within a hyphenated term, "low-carbon." Low-carbon is usually a shorthand for gas.
Renewable is Doable contains another set of words 6 times: "Jack Gibbons." Jack Gibbons is the principal at the Ontario Clean Air Alliance (OCAA) - another nominally non-governmental organization that seems to leverage donations from the gas industry to procure government funding (as does Pembina).
Anthropogenic global warming/AGW/Global warming isn't in the document.
.png) |
| The relationship: high nuclear production to low emissions |
Carbon pricing is not assumed in the document; the concept isn't even broached. The "low carbon" "green energy portfolio" in the new Greenpeace/Pembina/OCAA could increase emissions from Ontario's electricity sector by 25%.
[7]Renewable is doable does note "greenhouse gas (GHG) emissions" twice; once in noting how they went up when the government took 7 nuclear units off-line late in the 1990's, and once in noting how they might rise during refurbishment outages at Darlington.
If Darlington units are offline for extended periods emissions will rise
If Bruce units are removed emissions will rise.
If 2000MW of nuclear capacity aren't built to replace the 3000MW at Pickering, emissions will rise.
Regional emissions will drop now that Point Lepreau is back operating
International emissions aren't only lowered by CANDU technology in Canada, but in Argentina, Romania, China, Korea and India.
All of these units, including India's domestic heavy-water reactors, flowed from a choice to develop nuclear energy here, in Ontario.
ConclusionsThe analysis in the Greenpeace/Pembina/Ontario Clean Air Alliance report does not take environmental externality costs into account, exposing the non-environmental non-governmental organizations as common lobbyists.
Their "portfolio of conservation and green energy" is not properly costed for Ontario, and does not provide the necessary firm capability to meet peak demand in winter, or the other secondary peak on summer evenings.
Their use of weighted average pricing for vRES (wind and solar) is demonstrably flawed
[8], as the value of those sources declines rapidly as their share of generation increases; their costing of dispatchable bioenergies, and CHP, is also flawed in that it assumes high capacity factors for sources presumably existing to operate only when demand exists and wind and solar generation does not meet it.
[9] Cost, and cost overruns are a valid concern, but if cost really is a primary concern it must be noted the cheapest electricity contracted in recent years are the refurbished/reworked models at Bruce A - as well as emphasizing Darlington's output remains far cheaper than the private, primarily gas, supply contracted from non-utility generators around the same time Darlington was under construction.
These are realities.
It's also a reality that if present trends continue Ontario will have periods of excess generation if today's 13,000 MW of nuclear capacity is reduced to 12,000MW.
If present trends continue summer peaks will likely also rise along with the widely expected increase in temperatures.
If more processes are electrified, Ontario will contribute less to the atmosphere's greenhouse gas component. In 2011 Ontario reportedly emitted 14,800kt CO2e in generating electricity - less than the 20,000CO2e emitted in residential uses (ie. furnaces, water heater), and far less than the 45,300 kt CO2e from road transportation.
If Ontario is considering the environment in a Long Term Energy Plan, the discussion on energy needs to be broadened beyond how to constrain electricity usage.
The Darlington new build may be a questionable proposition if the discussion is only about what we expect is going to happen to us.
If the discussion becomes about the things we know how to accomplish that contibute to the changes we want to make, we will want more processes electrified.
We should want as much electricity to come from the clean baseload created with a technology developed domestically; one which has put us in a position where the intensity of our emissions from electricity is a fraction of that in the far more expensive states NENGOs would have us emulate.
ENDNOTES
[1] This is not an "apples to apples" comparison as the metered data would, presumably, not include line loss and the IESO's reporting of Ontario Demand isn't really reporting demand, but supply (thus including line loss). Compounding data integrity issues, December 2001 was omitted from the metered data set (so I copied over December 2000's total for estimating), and, particularly, the IESO's data quality has been rapidly degrading with the growth in embedded generators - generation that displaces the requirement from the gnerators on the IESO system, and therefore that generation shows as declining demand .
For another view of demand changes see
this chart created for
Stranded Debt, Abandoned Responsibility.
[2] One reason to disrespect the IESO's forecasting abilities is their historical provision of low summer peaks under normal weather peak. For instance, they
forecast 22834MW as a normal weather peak for 2014 after
forecasting 23,103 as a normal weather peak for 2013's summer last September. That was exceeded on 5 days, with the peak on July 17th. The failure is likely that normally July 17th would not be so hot as to demand 25000MW - but some day in July/August would usually be warmer than it usually is, and demand close to 25000MW.
[3] Greenpeace must know of the efforts in conservation as they had a rookie MPP noting their conservation over nuclear energy policy back
in 1991:
Mr McGuinty: You must be aware that the coalition of environmental groups made up of Friends of the Earth, Greenpeace and the Nuclear Awareness Project are strongly opposing your appointment as chairman. I have a letter here dated 2 April 1991 to the Premier and they say, second paragraph, "Mr Eliesen has publicly taken a fundamentally pro-nuclear, anti-conservation position, and has been notably inactive in pursuing the government's proconservation and nuclear moratorium policies." They go on to say, "He has spurned meaningful public consultation."
Presumably the "proconservation and nuclear moratorium policies" were the NDP's, under then Premier Rae.
[4] The NUG were responsible for 22% of the unfunded liability - and I would guess 6-7% of annual generation.
I wrote on the non-utility generator issue in
Wynne should right Duguid's wrong NUG directive[5] The reference to, and context for, the quote is in
Duncan's Grow-Op Is Stealing Hydro[6] Readers of the Greenpeace/Pembina document may be surpised at when Mr. Jennings was called to the
hearing on April 7, 2011Mr. Jennings, over the past several days since you came and spoke to us and gave us your overview of the way the plans for development of energy resources and electrical generation resources in Ontario were put forward, we’ve had interventions from many of our intervenors concerning decisions on energy choices and the energy mix going forward, and the scope of the application brought forward by Ontario Power Generation. And we made reference, on more than one occasion, to the information that you presented to us.
But the concern on the part of many intervenors is that they did not see the rationale for the alternatives being proposed for the energy mix and on the true need for nuclear generation as opposed to alternatives.
So with that as introductory remarks, we’d like to get from you your perspectives on how the decision to go with nuclear as opposed to other choices was reached for the long-term?
[7] Amir Shalaby, of the OPA, delivered
a presentation late in 2012 which showed a forecast for 2015 including only 9 TWh from natural gas (slide 8); the 2.3TWh indicated for CHP in Renewable is Doable would not operate efficiently - at CCGT emission levels it would add about 25% of that figure.
[
8]
The diminishing value, and increasing costs, of wind and solar generation in Ontario[
9]
The Real High Price of Low-Value Electricity, and
The Capacity Trap: Ontario's Electricity Costs Soar as Emissions Drop